Guangdong Qingyuan Yingde project undertaken by our company has achieved the goal of "putting both 1 and 2 combustion engine units into operation". A grand recognition activity was held on March 11. Comrade Pan Bin, the mayor of Qingyuan, and Comrade Peng Liang, the secretary of Yingde New District Management Committee, attended and delivered important speeches. Li Youdong, manager of geotechnical engineering company, Zhang Liang, deputy manager of geotechnical engineering company, and Gu Xiguang, project manager, were invited to participate in the event. At the recognition conference, our company was awarded the " Merit Award of Huadian Qingyuan Cogeneration Construction Project (2×9F class)", and project manager Gu Xiguang won the " Huadian Qingyuan (2×9F class) Project Construction Meritorious Individual Award”.
The pile foundation construction of Huadian Yingde project started in November 2018 and was completed on November 3, 2019. The construction lasted for more than 350 days. The whole plant was built into 2 units, involving 14 construction parts, with a total number of 994 piles. During the construction process, all members of our project department fought against the heat and wind, faced up to difficulties and overcame challenges, actively improved the construction technology and improved the drilling progress with maximum efficiency. During the peak period, we invested 14 large rotary drilling rigs and more than 170 manpower, which made our company highly praised by the leaders of Huadian Qingyuan Company and made outstanding contributions to the smooth progress of Huadian Qingyuan project.